The construction of 2 x (400 kV + 110 kV) transmission line Toivila - Hikiä, part 3
The construction of 2 x (400 kV + 110 kV) transmission line Toivila - Hikiä, part 3 Fingrid Oyj has decided to build new 2 x (400 kV + 110 kV) power lines between Toivila and Hikiä substations. The new transmission lines will be mostly located in the place of the existing 110 kV power lines. Both new transmission lines will be constructed with 400 kV + 110 kV structures. Only 400 kV conductors will be installed on the western transmission line (design code 2055). Both 400 kV and 110 kV conductors will be installed on the eastern transmission line (design codes 2084 and 2085). The length of…
- Ostaja
- Fingrid Oyj
- Julkaistu
- 2026-06-30
- Arvo
- 40 795 669 EUR
- Ilmoitus
- 52670
Voittajat ja hankinnan osat
The construction of 2 x (400 kV + 110 kV) transmission line Toivila - Hikiä, part 3
Fingrid Oyj has decided to build new 2 x (400 kV + 110 kV) power lines between Toivila and Hikiä substations. The new transmission lines will be mostly located in the place of the existing 110 kV power lines. Both new transmission lines will be constructed with 400 kV + 110 kV structures. Only 400 kV conductors will be installed on the western transmission line (design code 2055). Both 400 kV and 110 kV conductors will be installed on the eastern transmission line (design codes 2084 and 2085)…
- LEONHARD WEISS OÜ (EE101756486) – 40 795 669 €