The construction of 400 kV + 110 kV transmission line Alajärvi - Petäjävesi
The construction of 400 kV + 110 kV transmission line Alajärvi - Petäjävesi Fingrid Oyj is requesting Tender for the construction of transmission line 400 kV + 110 kV between Alajärvi and Petäjävesi substation along with necessary modifications to the existing network. The 110 kV line ends at the substations but the 400 kV line bypasses both stations. The length of line route is app. 100 km.,
- Ostaja
- Fingrid Oyj
- Julkaistu
- 2025-11-23
- Arvo
- 26 468 700 EUR
- Suorituspaikka
- Satakunta
- Ilmoitus
- 34693
Voittajat ja hankinnan osat
The construction of 400 kV + 110 kV transmission line Alajärvi - Petäjävesi
Fingrid Oyj is requesting Tender for the construction of transmission line 400 kV + 110 kV between Alajärvi and Petäjävesi substation along with necessary modifications to the existing network. The 110 kV line ends at the substations but the 400 kV line bypasses both stations. The length of line route is app. 100 km.
- Enersense PN Oy (2598027-9) – 26 468 700 €